A19/A182 roadworks


Along with our contractor, BAM Nuttall, we have started works to improve traffic flow and enhance capacity at the A19 / A182 junction, to facilitate commercial development at Jade business park and in the local area.

The improvements will support the expansion of the business park, allowing for the creation of an additional 500,000 sq ft of commercial space and up to 2,000 jobs. These works as well as forthcoming capacity improvements at the Dalton Park Signals will also improve the traffic flow and journey times for general traffic. Improved pedestrian and cyclist connections will be implemented as part of this scheme. 

Works that will be completed

The dumbbell roundabouts on each side of the A19 will be removed and converted  into signalised junctions, with dedicated crossing facilities for pedestrians and cyclists. The existing number of traffic lanes on the A182 bridge, spanning the A19, will be increased, with widening also occurring on approaches to the junction. A new standalone cycle / footbridge spanning the A19 will also be implemented.

 

A19/A182 – Highway Improvement Works (PDF, 676 KB)

Visualisation of completed scheme

A19/A182 Jade Junction visualisation of completed scheme transcript (PDF, 8 KB)

Upcoming programme of works and diversions

Preparatory works have already been undertaken with the scheme programmed for completion spring 2025. 

PhaseProposed traffic managementTimeExpected startExpected endDiversion and diversion distance
A19 northbound off slip road widening

Lane closure

24 hourApril 2024January 2025    
A19 southbound off slip road wideningLane 2 closure24 hour24 October 2024Mid-December 2024 
A19 southbound off slip road barrier installFull closure 8.00pm - 6.00am (night time only)18 November 202423 November 2024Continue south on the A19 exiting at the Easington junction, u-turning at Littlethorpe roundabout, heading north on the A19 and exiting at Cold Hesledon. Diversion distance 6 miles
A19 southbound exit and entry slip Full closure8.00pm - 6.00am (night time only)25 November 20244 December 2024A19 exit slip: Continue south on the A19 exiting at the Easington junction, u-turning at Littlethorpe roundabout, heading north on the A19 and exiting at Cold Hesledon. Diversion distance 6 miles

A19 entry slip: Continue west on A182 overbridge then north on B1285. Continue north onto A19 exiting at the A1018 northbound, proceeding to Ryhope roundabout, turning onto the A1018 southbound, heading south on the A19 and exiting at Cold Hesledon.
Diversion distances 6.5 miles.
A19 northbound off slip Full closure8.00pm - 6.00am (night time only)4 December 20247 December 2024Continue north on the A19 exiting at the A1018 northbound, proceeding to Ryhope roundabout, turning onto the A1018 southbound, heading south on the A19 and exiting at Cold Hesledon.
Diversion distances 6.7 miles.
A19 southbound on slipFull closure8.00pm - 6.00am (night time only)4 December 20247 December 2024Continue west on A182 overbridge then north on B1285. Continue north onto A19 exiting at the A1018 northbound, proceeding to Ryhope roundabout, turning onto the A1018 southbound, heading south on the A19 and exiting at Cold Hesledon.
Diversion distances 6.5 miles.
A19 southbound off slip road barrier relocationFull closure 8.00pm - 6.00am7 December 20248 December 2024Continue south on the A19 exiting at the Easington junction, u-turning at Littlethorpe roundabout, heading north on the A19 and exiting at Cold Hesledon. Diversion distance 6 miles
A19 northbound off slip road barrier relocationFull closure8.00pm - 6.00am 8 December 20249 December 2024Continue north on the A19 exiting at the A1018 northbound, proceeding to Ryhope roundabout, turning onto the A1018 southbound, heading south on the A19 and exiting at Cold Hesledon.
Diversion distances 6.7 miles.

Note: Further phases of work are proposed in the vicinity of the A19/A182 junction until scheme completion, anticipated in Spring 2025. Details of future phases will be provided once information is available.

Some diversions for vehicles will be needed during specific construction phases. Localised pedestrian and cyclist diversions will be in place and signposted throughout the various phases of work.

One Network: A19/A182 diversions

Although some disruption is inevitable, we are doing everything possible to minimise the impact to businesses and residents, with phased work and night time closures where possible. Sometimes, the dates of road closures may change due to unforeseen circumstances but we will keep those affected informed.

Funding

The scheme is funded by the Local Growth Fund, Enterprise Zone Fund, Department for Transport, S106 funding and Durham County Council local funding.